Home : Training : Available Courses : Facility and ER Plan Testing
Scope of Training
1. Table top scenarios
2. Mock scenarios (small city wide)
3. Evacuation / ERP specific testing
The work to be performed by Quantum Murray LP will take the following approach:
All procedures will be reviewed to ensure that the plan meets the client's requirements and complies with NFPA and other standards applicable to the client's facility. Professional emergency service personnel will audit the program, to ensure compliance, and offer suggestions to ensure that the program meets the highest standards.
Timeline Estimates
Time for emergency plan review
2 Hours
Time for drill and debriefing each shift, 3 x 2 hours = 6 Hours
Time for report production
2 Hours
Timeline Goals
Time for project completion
10 Days